Earned value in plain words: are we on budget and on time?

By Mark Nii Barnor Adom · 7 min read ·

Saying "we have spent half the budget" tells you nothing if only a third of the work is done. Earned value fixes that by measuring progress in money, so you can compare it with what you spent.

The words

  • BAC (budget at completion): the whole approved budget.
  • PV (planned value): the value of the work you planned to have finished by today.
  • EV (earned value): the value of the work you have actually finished by today.
  • AC (actual cost): what you have really spent by today.

The four results

  • Cost variance (CV) = EV minus AC. Negative means over budget.
  • Schedule variance (SV) = EV minus PV. Negative means behind.
  • CPI = EV divided by AC. Below 1 means you get less than one cedi of work for each cedi spent.
  • SPI = EV divided by PV. Below 1 means behind plan.

A worked example (made-up numbers, in thousands of GHS)

Budget (BAC) is 200. By today you planned to be worth 45 (PV). The finished work is worth 40 (EV). You have spent 50 (AC).

  • CV = 40 minus 50 = minus 10 (over budget)
  • SV = 40 minus 45 = minus 5 (behind)
  • CPI = 40 / 50 = 0.80
  • SPI = 40 / 45 = 0.89

A simple forecast

If things carry on the same way, the final cost is EAC = BAC divided by CPI:

200 / 0.80 = 250. The project will probably end about 50 over budget.

What to do with it

  1. Look at the trend, not only today. A CPI falling each week is a warning.
  2. Act early. Cut scope, add a reserve request, fix the cause or tell the sponsor. Sponsors forgive bad news that comes early.
  3. Say it in a sentence. "We are over budget and a little late, and we forecast 250 against 200. Here are two options."
  4. Check your measures. EV only works if you agreed how to measure progress (for example, by finished deliverables, not "about 80% done").

When you do not need it

For a very small job, a simple table of planned against actual may be enough. Earned value helps most when the project is large, spread over weeks or paid in stages.