Float and slack explained: which tasks can run late and which cannot

By Mark Nii Barnor Adom · 6 min read ·

If you have ever heard "that task is on the critical path" and nodded without knowing what it meant, this is for you.

The two words

Float and slack are the same thing: the number of days a task can be late without delaying the end of the project.

The critical path is the chain of tasks that has no float. If any task on it slips, the finish date slips.

A worked example (made-up numbers)

A small project has four tasks:

  • A: Prepare the site takes 3 days and goes first.
  • B: Order fittings takes 2 days and starts after A.
  • C: Build the frame takes 4 days and starts after A.
  • D: Finish and hand over takes 2 days and starts after both B and C are done.

There are two routes through the work:

  • A, then B, then D: 3 + 2 + 2 = 7 days
  • A, then C, then D: 3 + 4 + 2 = 9 days

The project cannot finish before the longest route. So the project takes 9 days, and the critical path is A, C, D.

Task B is not on that path. It could take 2 days longer (so route A, B, D also becomes 9 days) and nothing changes. Its float is 9 minus 7, which is 2 days.

The formula

Float = Late start minus Early start (or Late finish minus Early finish).

Tasks with float of zero are critical.

How to use it

  1. Protect the critical tasks. Give them your best people and check them first each day.
  2. Use float on purpose. If a supplier is late on task B, you have 2 days before it matters. Decide whether to chase or wait.
  3. Recheck when anything moves. Float is shared along a chain. If B uses its 2 days, the tasks after it lose theirs.
  4. Do not hide float. Padding every task makes the plan look long and makes people relax.

Where it shows up in real work

Pouring a concrete floor, then waiting for it to cure, is often critical. Painting a room that is not blocking anything may have float. Ask of every delay: "Is this task on the critical path?" If yes, act today. If no, note how much float is left.

The Project Management pathway teaches the critical path with exercises, and explains every formula (what it means, the steps and a worked example). For the money side of the same thinking, see earned value in plain words.