A project charter is a short document that says why a project exists, what it will deliver and who has the power to decide. It is the first paper you write, and it is the one you will point to when someone says, three months later, "I thought we agreed something different."

Why a charter matters

Most disagreements on a project are about things nobody wrote down: what is included, who approves, how much money there is. A charter puts those answers on one page, signed by the person who is paying or sponsoring.

The ten things to put in it

  1. Purpose. Why are we doing this? One or two sentences.
  2. Objectives and success measures. What will be true when it works? Use numbers where you can ("open by 1 March", "under GHS 150,000").
  3. Scope: in. What the project will deliver.
  4. Scope: out. What it will not deliver. This line prevents the most arguments.
  5. Key deliverables. The main things you hand over.
  6. Milestones. Three to six dates that matter.
  7. Budget summary. The total, and who controls it.
  8. Main risks. The top three things that could go wrong.
  9. People and roles. Sponsor, project manager, key team members, and who must approve changes.
  10. Assumptions and constraints. What you are relying on (for example, "approvals within 14 days") and what limits you (a fixed date, a fixed budget).

A simple template

Copy this and fill it in:

  • Project name:
  • Sponsor / client:
  • Project manager:
  • Purpose (why):
  • Success measures:
  • In scope:
  • Out of scope:
  • Deliverables:
  • Milestones and dates:
  • Budget and who approves spending:
  • Top three risks:
  • Assumptions and constraints:
  • Approved by (name, date):

Tips for Ghanaian projects

  • Write the approval path down. Who signs off, and how many days do they have? Late approvals are one of the most common causes of delay.
  • If a landlord, a ministry, a community or a chief must agree, name them as stakeholders on day one.
  • Keep it to one page. A charter nobody reads is useless.

Where to go next

A charter leads straight into stakeholders and scope. Read how to handle scope creep, and see the working order of documents in our Project Management pathway, which includes a charter lesson and a ready-made template for every step. Examples in the course use made-up names and numbers.