Project Management

Scope creep: how to say yes, no or later to a client

By Mark Nii Barnor Adom · 6 min read ·

Scope creep is when a project quietly grows: "can you also add this?", "it should be a small thing", "we assumed that was included". Each request seems fair. Together they eat your time, your budget and your goodwill.

Why it happens

  • The scope was never written clearly.
  • "Out of scope" was never discussed.
  • Nobody priced the extra work, so it felt free.
  • You wanted to be helpful.

Step one: write the scope and the exclusions

Before work starts, agree in writing what is in and what is out. A charter or a statement of work does this. See what to include in a project charter.

Step two: use a simple change process

When something new is asked:

  1. Write it down. One line: what is being asked and by whom.
  2. Check the impact. How much extra time, cost and risk?
  3. Give the client the choice. Yes, no or later (see below).
  4. Record the decision and update the plan if it was approved.

Yes, no or later

  • Yes, with a price and a date. "We can add that. It adds GHS 3,500 and two days. Shall I go ahead?"
  • No, for a reason. "That is outside what we agreed, and it would put the launch date at risk."
  • Later. "Let's add it to a second phase. I will note it now so it is not lost."

A worked example (made-up)

You are building a small clinic website for GHS 20,000. The client asks for an online booking feature that was not in the plan. You estimate two weeks and GHS 6,000.

If you quietly do it, your margin drops. If you refuse, you may lose the relationship. The change process gives a third path: show the price and the date, and let the client choose yes or later.

Words that help

  • "I would love to include that. Let me check what it does to the timeline and cost, and come back to you today."
  • "Here are two options: add it now at this price, or place it in phase two."

Keep your relationship

Say yes to small things that cost you little, and note them. People remember generosity, and you keep a record for when the big requests arrive.

The Project Management pathway has a change-control lesson, a lesson on difficult conversations (scope creep, late payment, stuck sponsors) and a change request template. Related reading: margin or markup, since every extra feature should be priced with a real margin.

Written by Mark Nii Barnor Adom. About the author