A risk is something that may happen and would hurt the project if it did. A risk register is the list of them, with a plan for each. It takes about half an hour to build a useful first version.
The columns
- ID: R-01, R-02 and so on
- Risk: what could go wrong, for example "Supplier delivers late"
- Cause: why it might happen
- Probability: 1 to 5
- Impact: 1 to 5
- Score: probability times impact
- Response: what you will do
- Owner: one named person
- Status: open, watching or closed
How to score
Give each risk a probability from 1 (very unlikely) to 5 (very likely) and an impact from 1 (minor) to 5 (severe). Multiply them. A risk scoring 20 deserves attention before one scoring 4.
Expected money value
For risks you can price, work out an expected money value (EMV):
EMV = Probability times the cost if it happens
Example (made-up): there is a 30% chance a late approval costs you GHS 20,000 in waiting time. EMV = 0.30 x 20,000 = GHS 6,000. That is a sensible amount to hold in reserve for that risk.
The four responses
- Avoid: change the plan so the risk cannot happen.
- Reduce: make it less likely or less painful.
- Transfer: move it to someone else (insurance, a contract clause).
- Accept: do nothing now, but keep a reserve or a backup.
Risks that often appear on projects in Ghana
These are examples to prompt your thinking, not a complete list:
- Approvals or permits taking longer than planned
- Rain delaying outdoor work
- A supplier or contractor delivering late
- Exchange rate changes on imported items
- A key person leaving or falling ill
- Power or internet outages during a launch
Habits that make it work
- Give every risk one owner. A risk with no owner is a worry, not a plan.
- Review it weekly. Add new risks, close old ones, update the scores.
- Keep it short. Ten well-managed risks beat fifty ignored ones.
- Tell the sponsor about the top three, in plain words.
The Project Management pathway has a risk lesson, a risk register template, a heat map and a RAID log, each with a made-up example. See also what goes in a project charter, where the top three risks are first written down.
Written by Mark Nii Barnor Adom. About the author