Project Management

How to build a simple project risk register

By Mark Nii Barnor Adom · 6 min read ·

A risk is something that may happen and would hurt the project if it did. A risk register is the list of them, with a plan for each. It takes about half an hour to build a useful first version.

The columns

  • ID: R-01, R-02 and so on
  • Risk: what could go wrong, for example "Supplier delivers late"
  • Cause: why it might happen
  • Probability: 1 to 5
  • Impact: 1 to 5
  • Score: probability times impact
  • Response: what you will do
  • Owner: one named person
  • Status: open, watching or closed

How to score

Give each risk a probability from 1 (very unlikely) to 5 (very likely) and an impact from 1 (minor) to 5 (severe). Multiply them. A risk scoring 20 deserves attention before one scoring 4.

Expected money value

For risks you can price, work out an expected money value (EMV):

EMV = Probability times the cost if it happens

Example (made-up): there is a 30% chance a late approval costs you GHS 20,000 in waiting time. EMV = 0.30 x 20,000 = GHS 6,000. That is a sensible amount to hold in reserve for that risk.

The four responses

  • Avoid: change the plan so the risk cannot happen.
  • Reduce: make it less likely or less painful.
  • Transfer: move it to someone else (insurance, a contract clause).
  • Accept: do nothing now, but keep a reserve or a backup.

Risks that often appear on projects in Ghana

These are examples to prompt your thinking, not a complete list:

  • Approvals or permits taking longer than planned
  • Rain delaying outdoor work
  • A supplier or contractor delivering late
  • Exchange rate changes on imported items
  • A key person leaving or falling ill
  • Power or internet outages during a launch

Habits that make it work

  1. Give every risk one owner. A risk with no owner is a worry, not a plan.
  2. Review it weekly. Add new risks, close old ones, update the scores.
  3. Keep it short. Ten well-managed risks beat fifty ignored ones.
  4. Tell the sponsor about the top three, in plain words.

The Project Management pathway has a risk lesson, a risk register template, a heat map and a RAID log, each with a made-up example. See also what goes in a project charter, where the top three risks are first written down.